January 2023
CO.ME.A. started the installation of two degassing vessels for our customer in Koln, Germany. The activities will have a duration of 12 months. Severino Santilli, our Site Manager is already on site to lead and coordinate our engineering and technical staff. The planning, as explained by our Project Manager Alessandro Bastianelli is to commission the first degassing vessel in July and the second machinery in September.
For CO.ME.A. each installation is the beginning of a new journey with the aim of employing skills, efforts and means to satisfy at maximum timing and needs of our loyal customers.